Asphalt surfacing RAMS and method statement template

A written starting point for a competent person to complete for the actual job.

Word downloads are built in your browser; no template input is stored or sent.

Template only. Must be reviewed and completed by a competent person for your site, task and conditions before use. Not a substitute for a site-specific assessment.
Project
[Project name]
Client
[Client name]
Job number
[Job number]
Location
[Site address and work area]
RAMS ref
[RAMS reference]
Revision
[Revision]
Work dates
[Start date] to [Finish date]
Prepared by
[Name / role]
Prepared date
[Date]
Reviewed by
[Competent reviewer name / role]
Reviewed date
[Date]
Approved by
[Authorised approver name / role]
Approved date
[Date]

Scope of works

  • Lay and compact [asphalt specification and area] using [paver and rollers], with controlled deliveries and safe public/traffic separation.
  • Complete [project], [client], [location], [dates], drawing/specification references and limits of the work. Review interfaces, ground and weather conditions before briefing.

Location and access

  • [Site address and exact work area]. [Delivery route, access times and site contact]. [Pedestrian routes, welfare and muster point].
  • Confirm public interfaces, nearby structures, overhead/buried services and any restricted areas. Keep emergency access open.

Sequence of works

  1. Confirm specification, weather limits, levels and traffic plan; brief crew and delivery drivers.
  2. Inspect the formation, drainage and bond-coat requirements; establish exclusion zones and safe walking routes.
  3. Check paver, rollers, guards and warning devices; agree communications and vehicle approach arrangements.
  4. Apply bond coat using the approved method and COSHH controls; restrict access until ready for surfacing.
  5. Receive asphalt with controlled truck-to-paver movements; keep people clear of hopper, augers and reversing vehicles.
  6. Lay to the specified thickness and temperature range; use suitable tools and avoid contact with hot materials.
  7. Compact using the approved rolling pattern while maintaining plant separation, safe edges and exposure controls.
  8. Finish joints and levels, inspect and test; reopen only after the surface is suitable and traffic controls are safely removed.

Plant and equipment

  • Paver and suitable rollers
  • Temperature/checking equipment
  • Bond-coat equipment
  • Suitable rakes and hand tools
  • Traffic barriers and spill kit

Materials and substances

  • Asphalt, bitumen emulsion and bond coat: current safety data and COSHH assessments
  • Fuel and oils: COSHH assessment
  • No unapproved diesel use as a release agent

Labour and competence

  • [Supervisor name], [team names and roles]. Check relevant skills, experience and current cards/tickets: CSCS or equivalent where required, and task-specific competence. A card alone does not prove competence for this task.
  • Competent surfacing supervisor and paving crew
  • Trained paver/roller operators with suitable competence evidence
  • NRSWA competence and traffic-management training where applicable

PPE

  • Safety helmet, high-visibility clothing and suitable protective footwear to the site rules.
  • Task-specific gloves and eye protection; waterproof alkali-resistant protection for wet cement and suitable heat protection for asphalt.
  • Hearing protection and assessed respiratory protection where required; tight-fitting RPE must be suitable and face-fit tested. Confirm [site PPE requirements].

Permits and checks

  • Approved traffic plan and highway permissions where required
  • Plant checks and delivery coordination
  • COSHH assessments and specified temperature/test records
  • Brief the completed RAMS before work; review after changes, incidents or unexpected conditions. Stop if controls cannot be maintained.

Emergency arrangements

  • Nearest A&E: [hospital name, address, route and travel time]. Site address for emergency services: [address, grid reference and access point]. Call 999 or 112 for an emergency.
  • First aiders: [names, phone numbers and locations]. First-aid kit: [location]. Muster point: [location]. Emergency coordinator: [name and number].
  • Spill kit: [location and type]. Service-owner emergency contacts: [numbers]. Agree [task-specific rescue arrangements] before work; do not enter an unsafe excavation or confined space to attempt rescue.

Environmental controls

  • Control fumes by work positioning and assessed ventilation
  • Contain bitumen spills; prevent entry into drains and manage waste asphalt
  • Prevent spills, silt and wash water entering drains or watercourses; follow [site pollution response].
  • Control dust, noise and vibration; segregate waste and use authorised disposal routes. Confirm [working hours], [waste arrangements] and [environmental permits].

References

  • Construction (Design and Management) Regulations 2015
  • HSG150 — Health and safety in construction
  • Provision and Use of Work Equipment Regulations 1998 (PUWER)
  • Control of Substances Hazardous to Health Regulations 2002 (COSHH)
  • Control of Noise at Work Regulations 2005
  • Control of Vibration at Work Regulations 2005
  • Safety at Street Works and Road Works — A Code of Practice
  • Traffic Signs Manual, Chapter 8 — Traffic safety measures and signs for road works and temporary situations

Risk assessment

Ratings are deliberately blank. A competent person must assess likelihood, severity and risk before and after controls for the actual site. Do not start until controls and any further actions have been agreed.

HazardWho might be harmedControl measuresBefore: LikelihoodBefore: SeverityBefore: RiskAfter: LikelihoodAfter: SeverityAfter: Risk
Hot asphalt or bitumen burnsSurfacing crew and drivers
  • Avoid direct contact; use suitable heat-resistant gloves, footwear and clothing.
  • Provide agreed burn first aid; do not remove stuck bitumen from skin.
Paver, roller and truck crush zonesCrew and drivers
  • Maintain exclusion zones at hopper and moving plant.
  • Use agreed signals; stop if visual contact or safe clearance is lost.
Fumes and skin contactSurfacing crew
  • Assess products and fumes; work upwind where practicable and limit exposure.
  • Use COSHH controls and washing facilities; avoid contaminated clothing.
Noise and vibrationPlant crew
  • Maintain machinery and assess exposure.
  • Apply hearing zones and suitable vibration controls.
Traffic and public accessCrew and road users
  • Install approved traffic controls and pedestrian routes.
  • Maintain and inspect segregation; do not reopen before safe cooling and completion.
Moving plant and delivery vehiclesOperatives, visitors and the public
  • Separate people from plant using barriers and agreed routes; maintain the operator’s visibility.
  • Use a trained banksman for restricted manoeuvres; stop if anyone enters the exclusion zone.
Slips, trips and fallsOperatives and visitors
  • Keep access routes firm, clear and lit; remove offcuts and trailing hoses.
  • Provide safe access and edge protection appropriate to the work area.
Fuel or hydraulic oil spillOperatives and nearby watercourses
  • Refuel in a designated area away from drains with drip trays and suitable spill kits.
  • Stop the source if safe, contain the spill and report it using [site spill procedure].

Hot asphalt or bitumen burns

Who: Surfacing crew and drivers

  • Avoid direct contact; use suitable heat-resistant gloves, footwear and clothing.
  • Provide agreed burn first aid; do not remove stuck bitumen from skin.

Before controls

Likelihood
Severity
Risk

After controls

Likelihood
Severity
Risk

Paver, roller and truck crush zones

Who: Crew and drivers

  • Maintain exclusion zones at hopper and moving plant.
  • Use agreed signals; stop if visual contact or safe clearance is lost.

Before controls

Likelihood
Severity
Risk

After controls

Likelihood
Severity
Risk

Fumes and skin contact

Who: Surfacing crew

  • Assess products and fumes; work upwind where practicable and limit exposure.
  • Use COSHH controls and washing facilities; avoid contaminated clothing.

Before controls

Likelihood
Severity
Risk

After controls

Likelihood
Severity
Risk

Noise and vibration

Who: Plant crew

  • Maintain machinery and assess exposure.
  • Apply hearing zones and suitable vibration controls.

Before controls

Likelihood
Severity
Risk

After controls

Likelihood
Severity
Risk

Traffic and public access

Who: Crew and road users

  • Install approved traffic controls and pedestrian routes.
  • Maintain and inspect segregation; do not reopen before safe cooling and completion.

Before controls

Likelihood
Severity
Risk

After controls

Likelihood
Severity
Risk

Moving plant and delivery vehicles

Who: Operatives, visitors and the public

  • Separate people from plant using barriers and agreed routes; maintain the operator’s visibility.
  • Use a trained banksman for restricted manoeuvres; stop if anyone enters the exclusion zone.

Before controls

Likelihood
Severity
Risk

After controls

Likelihood
Severity
Risk

Slips, trips and falls

Who: Operatives and visitors

  • Keep access routes firm, clear and lit; remove offcuts and trailing hoses.
  • Provide safe access and edge protection appropriate to the work area.

Before controls

Likelihood
Severity
Risk

After controls

Likelihood
Severity
Risk

Fuel or hydraulic oil spill

Who: Operatives and nearby watercourses

  • Refuel in a designated area away from drains with drip trays and suitable spill kits.
  • Stop the source if safe, contain the spill and report it using [site spill procedure].

Before controls

Likelihood
Severity
Risk

After controls

Likelihood
Severity
Risk

5 × 5 risk matrix key

5 × 5 key: Likelihood 1 Rare, 2 Unlikely, 3 Possible, 4 Likely, 5 Almost certain. Severity 1 Minor injury, 2 Injury requiring first aid, 3 Injury causing time off work, 4 Major injury or permanent disability, 5 Fatality. Risk = Likelihood × Severity (1–25). Use your organisation’s agreed action bands and acceptance criteria: [risk bands, actions and approval requirements].

L / S12345
112345
2246810
33691215
448121620
5510152025

Briefing record

[Briefing leader] · [Briefing date]. Confirm the completed RAMS and emergency arrangements have been understood.

NameCompanySignatureDate
[Name][Company][Signature][Date]
[Name][Company][Signature][Date]
[Name][Company][Signature][Date]
[Name][Company][Signature][Date]

More RAMS templates

  • Excavation and trenching RAMS template
  • Drainage pipelaying RAMS template
  • Manhole and chamber installation RAMS template
  • Kerbing and edging RAMS template
  • Concrete pour RAMS template
  • Working near buried services RAMS template
  • Sub-base placing and compaction RAMS template
  • Excavator lifting operations RAMS template
  • Temporary traffic management RAMS template

How this works

Complete every square-bracket placeholder, check the work sequence against your drawings and site conditions, and add missing hazards and controls. A competent person must assess every risk before and after controls and arrange review, approval and briefing before use.

These are plain-English starting points, not quoted guidance or a declaration of safety. Check current guidance, applicable legislation, manufacturer instructions and your organisation’s procedures.

Sources

  • Construction (Design and Management) Regulations 2015
  • HSG150 — Health and safety in construction
  • Provision and Use of Work Equipment Regulations 1998 (PUWER)
  • Control of Substances Hazardous to Health Regulations 2002 (COSHH)
  • Control of Noise at Work Regulations 2005
  • Control of Vibration at Work Regulations 2005
  • Safety at Street Works and Road Works — A Code of Practice
  • Traffic Signs Manual, Chapter 8 — Traffic safety measures and signs for road works and temporary situations

FAQs

What is a RAMS?

RAMS brings together a risk assessment and a method statement: the hazards, controls and planned sequence for a task.

Who should write and review it?

A competent person who understands the work, site and risks should complete and review it, involving the people who will do the work.

How often should it be reviewed?

Review before work starts and whenever the task, site, equipment, people or conditions change, or an incident shows controls may be inadequate. Follow your organisation’s review arrangements.

Is a template enough on its own?

No. Complete the site-specific details, assess the risks, check controls and arrange competent-person review, approval and a team briefing before use.

Why are the risk ratings blank?

Likelihood and severity depend on your actual site and controls. A competent person must fill them in; a generic score would not assess your job.

Draft this RAMS for your actual job in Civvio — it reads your drawings and specification and fills in the site-specific details for you to check.

Start free pilot

More free tools

  • Payment dates calculatorDue date, payment notice, pay less notice and final date under the Scheme or your contract.
  • Late payment interest calculatorStatutory interest at 8% over the reference rate, plus the fixed-sum compensation.
  • Working days calculatorDays between dates, or a date plus or minus days, for each UK nation.
  • Aggregate & concrete calculatorVolumes and tonnes with waste, plus concrete truck loads.
  • Pipe gradient calculatorConvert gradients, find the fall and invert levels along a run.
  • OS grid reference converterGrid references, eastings/northings and lat/long, both ways.
  • NEC4 compensation event timescalesTrack notification, quotation, failure-notice and assessment deadlines for an NEC4 ECC compensation event.
  • CIS deduction calculatorCalculate CIS deductions at 0%, 20% or 30%, qualifying direct costs, invoice VAT and net subcontractor payment.
  • VAT domestic reverse charge checkerCheck the UK construction VAT domestic reverse charge with a short CIS, VAT registration, end-user and staff-supply question flow.
  • Retention calculatorCalculate construction retention, caps and staged releases, or NEC X16 retention above the retention free amount.
  • Delay damages calculatorCalculate delay damages using calendar days or weeks, amended completion dates, daily or weekly rates and an optional cap.
  • Levelling reduction calculatorReduce levelling readings by rise and fall or height of collimation, check arithmetic and misclosure, adjust by setup and export CSV.
  • NEC X1 price adjustment calculatorCalculate NEC X1 PAF from user-entered indices, proportions and non-adjustable share, with Options A/B and C/D adjustment amounts.
  • NEC weather compensation event checkerCompare monthly NEC4 ECC weather measurements with 1-in-10-year values, identify excess and check the Contract Data location and completion context.
  • Adjudication timetableScheme referral, appointment, decision and correction deadlines.
  • Free RAMS and method statement templatesTen editable Word templates for common civils tasks — for competent-person review.
Civvio

Civil engineering, intelligently managed.

AI project engineering for civil engineering contractors — connecting drawings, site records, commercial events and project knowledge in one place.

Start free pilot View pricing →

Company

  • About
  • Pricing
  • Contact
  • Book a demo
  • Try the demo project

Product

  • Project Brain
  • Live voice
  • Commercial Watch
  • RAMS drafting
  • Contract Intelligence
  • Allocation

By role

  • Project managers
  • Site engineers
  • Site managers
  • Commercial teams
  • Directors

Free tools

  • Payment dates
  • Late payment interest
  • Working days
  • Material quantities
  • Pipe gradient & inverts
  • OS grid reference
  • NEC4 CE timescales
  • CIS deductions
  • VAT reverse charge
  • Retention
  • Delay damages
  • Levelling reduction
  • NEC X1 inflation
  • NEC weather CE
  • Adjudication
  • RAMS templates

Get in touch

  • hello@civvio.ai
  • Contact us
  • Book a demo
  • Explore a demo job

© 2026 Civvio. All rights reserved.