Free tools / Concrete pour

Concrete pour RAMS and method statement template

A written starting point for a competent person to complete for the actual job.

Word downloads are built in your browser; no template input is stored or sent.

Template only. Must be reviewed and completed by a competent person for your site, task and conditions before use. Not a substitute for a site-specific assessment.
Project
[Project name]
Client
[Client name]
Job number
[Job number]
Location
[Site address and work area]
RAMS ref
[RAMS reference]
Revision
[Revision]
Work dates
[Start date] to [Finish date]
Prepared by
[Name / role]
Prepared date
[Date]
Reviewed by
[Competent reviewer name / role]
Reviewed date
[Date]
Approved by
[Authorised approver name / role]
Approved date
[Date]

Scope of works

  • Place, vibrate and cure [concrete grade and volume] in [element/location] using [pump or skip]; confirm the formwork and placing design before pouring.
  • Complete [project], [client], [location], [dates], drawing/specification references and limits of the work. Review interfaces, ground and weather conditions before briefing.

Location and access

  • [Site address and exact work area]. [Delivery route, access times and site contact]. [Pedestrian routes, welfare and muster point].
  • Confirm public interfaces, nearby structures, overhead/buried services and any restricted areas. Keep emergency access open.

Sequence of works

  1. Confirm drawings, pour plan, concrete specification, weather, access and competence; brief the team.
  2. Inspect formwork, falsework and reinforcement against the design; obtain the required temporary works release or permit to load.
  3. Prepare stable delivery and plant positions; check overhead hazards, pump outriggers or skip lifting arrangements and exclusion zones.
  4. Inspect hoses, clamps and guards; agree communications and safe pump priming or skip discharge arrangements.
  5. Receive concrete, check delivery details and specified tests; control vehicle movements with safe access for the driver.
  6. Place in the designed sequence and rate without overloading formwork; control hose whip, suspended skips and access edges.
  7. Vibrate with trained operators and assessed exposure; finish without kneeling in wet concrete and wash off splashes promptly.
  8. Apply curing and protection; contain washout, inspect the completed pour and remove supports only with the agreed strength and release.

Plant and equipment

  • Concrete pump with inspected hoses/clamps or rated skip and crane
  • Designed formwork/falsework
  • Poker vibrators with inspected leads
  • Testing and finishing equipment
  • Washout container and barriers

Materials and substances

  • Ready-mix concrete and cement: COSHH assessment
  • Admixtures and curing compounds: current safety data and COSHH assessment
  • Fuel and hydraulic oil: COSHH assessment

Labour and competence

  • [Supervisor name], [team names and roles]. Check relevant skills, experience and current cards/tickets: CSCS or equivalent where required, and task-specific competence. A card alone does not prove competence for this task.
  • Competent concrete supervisor and placing crew
  • Trained pump operator or crane operator and slinger/signaller
  • Temporary works coordinator and competent formwork inspectors

PPE

  • Safety helmet, high-visibility clothing and suitable protective footwear to the site rules.
  • Task-specific gloves and eye protection; waterproof alkali-resistant protection for wet cement and suitable heat protection for asphalt.
  • Hearing protection and assessed respiratory protection where required; tight-fitting RPE must be suitable and face-fit tested. Confirm [site PPE requirements].

Permits and checks

  • Pour permit and temporary works inspection/permit to load
  • Pump setup assessment or skip lift plan
  • Service/overhead checks; concrete delivery and test records
  • Brief the completed RAMS before work; review after changes, incidents or unexpected conditions. Stop if controls cannot be maintained.

Emergency arrangements

  • Nearest A&E: [hospital name, address, route and travel time]. Site address for emergency services: [address, grid reference and access point]. Call 999 or 112 for an emergency.
  • First aiders: [names, phone numbers and locations]. First-aid kit: [location]. Muster point: [location]. Emergency coordinator: [name and number].
  • Spill kit: [location and type]. Service-owner emergency contacts: [numbers]. Agree [task-specific rescue arrangements] before work; do not enter an unsafe excavation or confined space to attempt rescue.

Environmental controls

  • Use impermeable concrete washout containment; no washout into ground or drains
  • Control noise, vibration and curing-compound overspray
  • Prevent spills, silt and wash water entering drains or watercourses; follow [site pollution response].
  • Control dust, noise and vibration; segregate waste and use authorised disposal routes. Confirm [working hours], [waste arrangements] and [environmental permits].

References

  • Construction (Design and Management) Regulations 2015
  • HSG150 — Health and safety in construction
  • BS 5975 series — Temporary works procedures and falsework (check current applicable part and edition)
  • Lifting Operations and Lifting Equipment Regulations 1998 (LOLER)
  • BS 7121 series — Safe use of cranes (check applicable part and edition)
  • Provision and Use of Work Equipment Regulations 1998 (PUWER)
  • Control of Substances Hazardous to Health Regulations 2002 (COSHH)
  • Control of Noise at Work Regulations 2005
  • Control of Vibration at Work Regulations 2005
  • Work at Height Regulations 2005 — HSE guidance

Risk assessment

Ratings are deliberately blank. A competent person must assess likelihood, severity and risk before and after controls for the actual site. Do not start until controls and any further actions have been agreed.

HazardWho might be harmedControl measuresBefore: LikelihoodBefore: SeverityBefore: RiskAfter: LikelihoodAfter: SeverityAfter: Risk
Formwork failurePour crew and nearby workers
  • Check designed supports and obtain release before loading.
  • Control pour rate and sequence; stop for movement, leakage or distortion.
Pump hose whip or line failurePlacing crew
  • Check hoses and clamps; maintain the exclusion area during priming and blockage clearance.
  • Depressurise and follow the manufacturer’s procedure before opening lines.
Suspended skip or vehicle movementCrew and drivers
  • Use a planned lift and exclusion zone; no people under skips.
  • Separate delivery traffic and operatives.
Wet concrete burns and eye contactPlacing and finishing crew
  • Wear waterproof alkali-resistant gloves, boots and eye protection.
  • Avoid kneeling in wet concrete; wash immediately and follow first-aid guidance.
Vibration or falls at edgesConcrete crew
  • Assess and limit vibrator exposure; use suitable maintained equipment.
  • Provide guarded work platforms and protected edges.
Moving plant and delivery vehiclesOperatives, visitors and the public
  • Separate people from plant using barriers and agreed routes; maintain the operator’s visibility.
  • Use a trained banksman for restricted manoeuvres; stop if anyone enters the exclusion zone.
Slips, trips and fallsOperatives and visitors
  • Keep access routes firm, clear and lit; remove offcuts and trailing hoses.
  • Provide safe access and edge protection appropriate to the work area.
Fuel or hydraulic oil spillOperatives and nearby watercourses
  • Refuel in a designated area away from drains with drip trays and suitable spill kits.
  • Stop the source if safe, contain the spill and report it using [site spill procedure].

Formwork failure

Who: Pour crew and nearby workers

  • Check designed supports and obtain release before loading.
  • Control pour rate and sequence; stop for movement, leakage or distortion.

Before controls

Likelihood
Severity
Risk

After controls

Likelihood
Severity
Risk

Pump hose whip or line failure

Who: Placing crew

  • Check hoses and clamps; maintain the exclusion area during priming and blockage clearance.
  • Depressurise and follow the manufacturer’s procedure before opening lines.

Before controls

Likelihood
Severity
Risk

After controls

Likelihood
Severity
Risk

Suspended skip or vehicle movement

Who: Crew and drivers

  • Use a planned lift and exclusion zone; no people under skips.
  • Separate delivery traffic and operatives.

Before controls

Likelihood
Severity
Risk

After controls

Likelihood
Severity
Risk

Wet concrete burns and eye contact

Who: Placing and finishing crew

  • Wear waterproof alkali-resistant gloves, boots and eye protection.
  • Avoid kneeling in wet concrete; wash immediately and follow first-aid guidance.

Before controls

Likelihood
Severity
Risk

After controls

Likelihood
Severity
Risk

Vibration or falls at edges

Who: Concrete crew

  • Assess and limit vibrator exposure; use suitable maintained equipment.
  • Provide guarded work platforms and protected edges.

Before controls

Likelihood
Severity
Risk

After controls

Likelihood
Severity
Risk

Moving plant and delivery vehicles

Who: Operatives, visitors and the public

  • Separate people from plant using barriers and agreed routes; maintain the operator’s visibility.
  • Use a trained banksman for restricted manoeuvres; stop if anyone enters the exclusion zone.

Before controls

Likelihood
Severity
Risk

After controls

Likelihood
Severity
Risk

Slips, trips and falls

Who: Operatives and visitors

  • Keep access routes firm, clear and lit; remove offcuts and trailing hoses.
  • Provide safe access and edge protection appropriate to the work area.

Before controls

Likelihood
Severity
Risk

After controls

Likelihood
Severity
Risk

Fuel or hydraulic oil spill

Who: Operatives and nearby watercourses

  • Refuel in a designated area away from drains with drip trays and suitable spill kits.
  • Stop the source if safe, contain the spill and report it using [site spill procedure].

Before controls

Likelihood
Severity
Risk

After controls

Likelihood
Severity
Risk

5 × 5 risk matrix key

5 × 5 key: Likelihood 1 Rare, 2 Unlikely, 3 Possible, 4 Likely, 5 Almost certain. Severity 1 Minor injury, 2 Injury requiring first aid, 3 Injury causing time off work, 4 Major injury or permanent disability, 5 Fatality. Risk = Likelihood × Severity (1–25). Use your organisation’s agreed action bands and acceptance criteria: [risk bands, actions and approval requirements].

L / S12345
112345
2246810
33691215
448121620
5510152025

Briefing record

[Briefing leader] · [Briefing date]. Confirm the completed RAMS and emergency arrangements have been understood.

NameCompanySignatureDate
[Name][Company][Signature][Date]
[Name][Company][Signature][Date]
[Name][Company][Signature][Date]
[Name][Company][Signature][Date]

More RAMS templates

  • Excavation and trenching RAMS template
  • Drainage pipelaying RAMS template
  • Manhole and chamber installation RAMS template
  • Kerbing and edging RAMS template
  • Working near buried services RAMS template
  • Sub-base placing and compaction RAMS template
  • Asphalt surfacing RAMS template
  • Excavator lifting operations RAMS template
  • Temporary traffic management RAMS template

How this works

Complete every square-bracket placeholder, check the work sequence against your drawings and site conditions, and add missing hazards and controls. A competent person must assess every risk before and after controls and arrange review, approval and briefing before use.

These are plain-English starting points, not quoted guidance or a declaration of safety. Check current guidance, applicable legislation, manufacturer instructions and your organisation’s procedures.

Sources

  • Construction (Design and Management) Regulations 2015
  • HSG150 — Health and safety in construction
  • BS 5975 series — Temporary works procedures and falsework (check current applicable part and edition)
  • Lifting Operations and Lifting Equipment Regulations 1998 (LOLER)
  • BS 7121 series — Safe use of cranes (check applicable part and edition)
  • Provision and Use of Work Equipment Regulations 1998 (PUWER)
  • Control of Substances Hazardous to Health Regulations 2002 (COSHH)
  • Control of Noise at Work Regulations 2005
  • Control of Vibration at Work Regulations 2005
  • Work at Height Regulations 2005 — HSE guidance

FAQs

What is a RAMS?

RAMS brings together a risk assessment and a method statement: the hazards, controls and planned sequence for a task.

Who should write and review it?

A competent person who understands the work, site and risks should complete and review it, involving the people who will do the work.

How often should it be reviewed?

Review before work starts and whenever the task, site, equipment, people or conditions change, or an incident shows controls may be inadequate. Follow your organisation’s review arrangements.

Is a template enough on its own?

No. Complete the site-specific details, assess the risks, check controls and arrange competent-person review, approval and a team briefing before use.

Why are the risk ratings blank?

Likelihood and severity depend on your actual site and controls. A competent person must fill them in; a generic score would not assess your job.

Draft this RAMS for your actual job in Civvio — it reads your drawings and specification and fills in the site-specific details for you to check.

Start free pilot

More free tools

  • Payment dates calculatorDue date, payment notice, pay less notice and final date under the Scheme or your contract.
  • Late payment interest calculatorStatutory interest at 8% over the reference rate, plus the fixed-sum compensation.
  • Working days calculatorDays between dates, or a date plus or minus days, for each UK nation.
  • Aggregate & concrete calculatorVolumes and tonnes with waste, plus concrete truck loads.
  • Pipe gradient calculatorConvert gradients, find the fall and invert levels along a run.
  • OS grid reference converterGrid references, eastings/northings and lat/long, both ways.
  • NEC4 compensation event timescalesTrack notification, quotation, failure-notice and assessment deadlines for an NEC4 ECC compensation event.
  • CIS deduction calculatorCalculate CIS deductions at 0%, 20% or 30%, qualifying direct costs, invoice VAT and net subcontractor payment.
  • VAT domestic reverse charge checkerCheck the UK construction VAT domestic reverse charge with a short CIS, VAT registration, end-user and staff-supply question flow.
  • Retention calculatorCalculate construction retention, caps and staged releases, or NEC X16 retention above the retention free amount.
  • Delay damages calculatorCalculate delay damages using calendar days or weeks, amended completion dates, daily or weekly rates and an optional cap.
  • Levelling reduction calculatorReduce levelling readings by rise and fall or height of collimation, check arithmetic and misclosure, adjust by setup and export CSV.
  • NEC X1 price adjustment calculatorCalculate NEC X1 PAF from user-entered indices, proportions and non-adjustable share, with Options A/B and C/D adjustment amounts.
  • NEC weather compensation event checkerCompare monthly NEC4 ECC weather measurements with 1-in-10-year values, identify excess and check the Contract Data location and completion context.
  • Adjudication timetableScheme referral, appointment, decision and correction deadlines.
  • Free RAMS and method statement templatesTen editable Word templates for common civils tasks — for competent-person review.
Civvio

Civil engineering, intelligently managed.

AI project engineering for civil engineering contractors — connecting drawings, site records, commercial events and project knowledge in one place.

Start free pilot View pricing →

Company

  • About
  • Pricing
  • Contact
  • Book a demo
  • Try the demo project

Product

  • Project Brain
  • Live voice
  • Commercial Watch
  • RAMS drafting
  • Contract Intelligence
  • Allocation

By role

  • Project managers
  • Site engineers
  • Site managers
  • Commercial teams
  • Directors

Free tools

  • Payment dates
  • Late payment interest
  • Working days
  • Material quantities
  • Pipe gradient & inverts
  • OS grid reference
  • NEC4 CE timescales
  • CIS deductions
  • VAT reverse charge
  • Retention
  • Delay damages
  • Levelling reduction
  • NEC X1 inflation
  • NEC weather CE
  • Adjudication
  • RAMS templates

Get in touch

  • hello@civvio.ai
  • Contact us
  • Book a demo
  • Explore a demo job

© 2026 Civvio. All rights reserved.