Free tools / Manhole and chamber installation

Manhole and chamber installation RAMS and method statement template

A written starting point for a competent person to complete for the actual job.

Word downloads are built in your browser; no template input is stored or sent.

Template only. Must be reviewed and completed by a competent person for your site, task and conditions before use. Not a substitute for a site-specific assessment.
Project
[Project name]
Client
[Client name]
Job number
[Job number]
Location
[Site address and work area]
RAMS ref
[RAMS reference]
Revision
[Revision]
Work dates
[Start date] to [Finish date]
Prepared by
[Name / role]
Prepared date
[Date]
Reviewed by
[Competent reviewer name / role]
Reviewed date
[Date]
Approved by
[Authorised approver name / role]
Approved date
[Date]

Scope of works

  • Install [precast chamber type and size], including base, rings, connections, benching and cover slab; entry into a confined space is outside this method unless separately planned.
  • Complete [project], [client], [location], [dates], drawing/specification references and limits of the work. Review interfaces, ground and weather conditions before briefing.

Location and access

  • [Site address and exact work area]. [Delivery route, access times and site contact]. [Pedestrian routes, welfare and muster point].
  • Confirm public interfaces, nearby structures, overhead/buried services and any restricted areas. Keep emergency access open.

Sequence of works

  1. Check chamber design, weights, ground conditions, services and permits; confirm the lifting and temporary works arrangements.
  2. Excavate with designed support and inspect before entry; provide edge protection and safe access.
  3. Prepare the foundation and base to the drawings; check level and bearing and allow required concrete strength before loading.
  4. Inspect lifting inserts and rated accessories; confirm the manufacturer’s lifting instructions and exclusion zone.
  5. Lift and place rings and slabs under a single agreed signaller; keep people clear of suspended loads and pinch points.
  6. Install connections, seals and benching from a safe position; assess cement contact and any chamber-entry requirement separately.
  7. Check alignment, connections and finish; backfill evenly in specified layers without displacing the chamber.
  8. Secure the cover, complete specified tests and record inspections; remove barriers only when the opening is safely closed.

Plant and equipment

  • Excavator or crane suitable for the planned lift
  • Manufacturer-approved ring lifters and rated accessories
  • Designed excavation support
  • Survey equipment
  • Concrete/benching tools

Materials and substances

  • Precast units, sealants and pipe connections
  • Cement mortar and concrete: COSHH assessment and washing facilities
  • Fuel and lubricants: COSHH assessment

Labour and competence

  • [Supervisor name], [team names and roles]. Check relevant skills, experience and current cards/tickets: CSCS or equivalent where required, and task-specific competence. A card alone does not prove competence for this task.
  • Competent lifting planner and supervisor
  • Trained operator and slinger/signaller
  • Experienced chamber installers
  • Confined-space trained team only where a separate entry plan requires it

PPE

  • Safety helmet, high-visibility clothing and suitable protective footwear to the site rules.
  • Task-specific gloves and eye protection; waterproof alkali-resistant protection for wet cement and suitable heat protection for asphalt.
  • Hearing protection and assessed respiratory protection where required; tight-fitting RPE must be suitable and face-fit tested. Confirm [site PPE requirements].

Permits and checks

  • Permit to dig, support design and inspections
  • Lift plan with unit weights, lifting points and ground bearing checks
  • Confined-space assessment; separate permit and rescue plan if entry is required
  • Brief the completed RAMS before work; review after changes, incidents or unexpected conditions. Stop if controls cannot be maintained.

Emergency arrangements

  • Nearest A&E: [hospital name, address, route and travel time]. Site address for emergency services: [address, grid reference and access point]. Call 999 or 112 for an emergency.
  • First aiders: [names, phone numbers and locations]. First-aid kit: [location]. Muster point: [location]. Emergency coordinator: [name and number].
  • Spill kit: [location and type]. Service-owner emergency contacts: [numbers]. Agree [task-specific rescue arrangements] before work; do not enter an unsafe excavation or confined space to attempt rescue.

Environmental controls

  • Contain cement washout in a designated impermeable area
  • Prevent contaminated or silty water entering drains
  • Prevent spills, silt and wash water entering drains or watercourses; follow [site pollution response].
  • Control dust, noise and vibration; segregate waste and use authorised disposal routes. Confirm [working hours], [waste arrangements] and [environmental permits].

References

  • Construction (Design and Management) Regulations 2015
  • HSG150 — Health and safety in construction
  • HSG47 — Avoiding danger from underground services
  • Lifting Operations and Lifting Equipment Regulations 1998 (LOLER)
  • BS 7121 series — Safe use of cranes (check applicable part and edition)
  • HSE — Excavations
  • BS 5975 series — Temporary works procedures and falsework (check current applicable part and edition)
  • Control of Substances Hazardous to Health Regulations 2002 (COSHH)
  • HSE — Confined spaces
  • HSE — Manual handling at work

Risk assessment

Ratings are deliberately blank. A competent person must assess likelihood, severity and risk before and after controls for the actual site. Do not start until controls and any further actions have been agreed.

HazardWho might be harmedControl measuresBefore: LikelihoodBefore: SeverityBefore: RiskAfter: LikelihoodAfter: SeverityAfter: Risk
Falling precast units or crushingLifting team and chamber installers
  • Check weights, lifting inserts and compatible accessories.
  • No one beneath suspended units; place from a protected position.
Open chamber or excavationOperatives and the public
  • Use designed support, secured access and edge protection.
  • Secure openings with rated covers or barriers when unattended.
Confined atmosphere or drowningAnyone entering a chamber
  • Avoid entry where possible; assess confined-space conditions.
  • Entry only under a separate competent plan with rescue equipment and trained attendants.
Wet cement burnsInstallers and finishers
  • Wear suitable waterproof alkali-resistant gloves and boots; prevent cement entering clothing.
  • Provide washing facilities and remove contaminated clothing promptly.
Moving plant and delivery vehiclesOperatives, visitors and the public
  • Separate people from plant using barriers and agreed routes; maintain the operator’s visibility.
  • Use a trained banksman for restricted manoeuvres; stop if anyone enters the exclusion zone.
Slips, trips and fallsOperatives and visitors
  • Keep access routes firm, clear and lit; remove offcuts and trailing hoses.
  • Provide safe access and edge protection appropriate to the work area.
Fuel or hydraulic oil spillOperatives and nearby watercourses
  • Refuel in a designated area away from drains with drip trays and suitable spill kits.
  • Stop the source if safe, contain the spill and report it using [site spill procedure].

Falling precast units or crushing

Who: Lifting team and chamber installers

  • Check weights, lifting inserts and compatible accessories.
  • No one beneath suspended units; place from a protected position.

Before controls

Likelihood
Severity
Risk

After controls

Likelihood
Severity
Risk

Open chamber or excavation

Who: Operatives and the public

  • Use designed support, secured access and edge protection.
  • Secure openings with rated covers or barriers when unattended.

Before controls

Likelihood
Severity
Risk

After controls

Likelihood
Severity
Risk

Confined atmosphere or drowning

Who: Anyone entering a chamber

  • Avoid entry where possible; assess confined-space conditions.
  • Entry only under a separate competent plan with rescue equipment and trained attendants.

Before controls

Likelihood
Severity
Risk

After controls

Likelihood
Severity
Risk

Wet cement burns

Who: Installers and finishers

  • Wear suitable waterproof alkali-resistant gloves and boots; prevent cement entering clothing.
  • Provide washing facilities and remove contaminated clothing promptly.

Before controls

Likelihood
Severity
Risk

After controls

Likelihood
Severity
Risk

Moving plant and delivery vehicles

Who: Operatives, visitors and the public

  • Separate people from plant using barriers and agreed routes; maintain the operator’s visibility.
  • Use a trained banksman for restricted manoeuvres; stop if anyone enters the exclusion zone.

Before controls

Likelihood
Severity
Risk

After controls

Likelihood
Severity
Risk

Slips, trips and falls

Who: Operatives and visitors

  • Keep access routes firm, clear and lit; remove offcuts and trailing hoses.
  • Provide safe access and edge protection appropriate to the work area.

Before controls

Likelihood
Severity
Risk

After controls

Likelihood
Severity
Risk

Fuel or hydraulic oil spill

Who: Operatives and nearby watercourses

  • Refuel in a designated area away from drains with drip trays and suitable spill kits.
  • Stop the source if safe, contain the spill and report it using [site spill procedure].

Before controls

Likelihood
Severity
Risk

After controls

Likelihood
Severity
Risk

5 × 5 risk matrix key

5 × 5 key: Likelihood 1 Rare, 2 Unlikely, 3 Possible, 4 Likely, 5 Almost certain. Severity 1 Minor injury, 2 Injury requiring first aid, 3 Injury causing time off work, 4 Major injury or permanent disability, 5 Fatality. Risk = Likelihood × Severity (1–25). Use your organisation’s agreed action bands and acceptance criteria: [risk bands, actions and approval requirements].

L / S12345
112345
2246810
33691215
448121620
5510152025

Briefing record

[Briefing leader] · [Briefing date]. Confirm the completed RAMS and emergency arrangements have been understood.

NameCompanySignatureDate
[Name][Company][Signature][Date]
[Name][Company][Signature][Date]
[Name][Company][Signature][Date]
[Name][Company][Signature][Date]

More RAMS templates

  • Excavation and trenching RAMS template
  • Drainage pipelaying RAMS template
  • Kerbing and edging RAMS template
  • Concrete pour RAMS template
  • Working near buried services RAMS template
  • Sub-base placing and compaction RAMS template
  • Asphalt surfacing RAMS template
  • Excavator lifting operations RAMS template
  • Temporary traffic management RAMS template

How this works

Complete every square-bracket placeholder, check the work sequence against your drawings and site conditions, and add missing hazards and controls. A competent person must assess every risk before and after controls and arrange review, approval and briefing before use.

These are plain-English starting points, not quoted guidance or a declaration of safety. Check current guidance, applicable legislation, manufacturer instructions and your organisation’s procedures.

Sources

  • Construction (Design and Management) Regulations 2015
  • HSG150 — Health and safety in construction
  • HSG47 — Avoiding danger from underground services
  • Lifting Operations and Lifting Equipment Regulations 1998 (LOLER)
  • BS 7121 series — Safe use of cranes (check applicable part and edition)
  • HSE — Excavations
  • BS 5975 series — Temporary works procedures and falsework (check current applicable part and edition)
  • Control of Substances Hazardous to Health Regulations 2002 (COSHH)
  • HSE — Confined spaces
  • HSE — Manual handling at work

FAQs

What is a RAMS?

RAMS brings together a risk assessment and a method statement: the hazards, controls and planned sequence for a task.

Who should write and review it?

A competent person who understands the work, site and risks should complete and review it, involving the people who will do the work.

How often should it be reviewed?

Review before work starts and whenever the task, site, equipment, people or conditions change, or an incident shows controls may be inadequate. Follow your organisation’s review arrangements.

Is a template enough on its own?

No. Complete the site-specific details, assess the risks, check controls and arrange competent-person review, approval and a team briefing before use.

Why are the risk ratings blank?

Likelihood and severity depend on your actual site and controls. A competent person must fill them in; a generic score would not assess your job.

Draft this RAMS for your actual job in Civvio — it reads your drawings and specification and fills in the site-specific details for you to check.

Start free pilot

More free tools

  • Payment dates calculatorDue date, payment notice, pay less notice and final date under the Scheme or your contract.
  • Late payment interest calculatorStatutory interest at 8% over the reference rate, plus the fixed-sum compensation.
  • Working days calculatorDays between dates, or a date plus or minus days, for each UK nation.
  • Aggregate & concrete calculatorVolumes and tonnes with waste, plus concrete truck loads.
  • Pipe gradient calculatorConvert gradients, find the fall and invert levels along a run.
  • OS grid reference converterGrid references, eastings/northings and lat/long, both ways.
  • NEC4 compensation event timescalesTrack notification, quotation, failure-notice and assessment deadlines for an NEC4 ECC compensation event.
  • CIS deduction calculatorCalculate CIS deductions at 0%, 20% or 30%, qualifying direct costs, invoice VAT and net subcontractor payment.
  • VAT domestic reverse charge checkerCheck the UK construction VAT domestic reverse charge with a short CIS, VAT registration, end-user and staff-supply question flow.
  • Retention calculatorCalculate construction retention, caps and staged releases, or NEC X16 retention above the retention free amount.
  • Delay damages calculatorCalculate delay damages using calendar days or weeks, amended completion dates, daily or weekly rates and an optional cap.
  • Levelling reduction calculatorReduce levelling readings by rise and fall or height of collimation, check arithmetic and misclosure, adjust by setup and export CSV.
  • NEC X1 price adjustment calculatorCalculate NEC X1 PAF from user-entered indices, proportions and non-adjustable share, with Options A/B and C/D adjustment amounts.
  • NEC weather compensation event checkerCompare monthly NEC4 ECC weather measurements with 1-in-10-year values, identify excess and check the Contract Data location and completion context.
  • Adjudication timetableScheme referral, appointment, decision and correction deadlines.
  • Free RAMS and method statement templatesTen editable Word templates for common civils tasks — for competent-person review.
Civvio

Civil engineering, intelligently managed.

AI project engineering for civil engineering contractors — connecting drawings, site records, commercial events and project knowledge in one place.

Start free pilot View pricing →

Company

  • About
  • Pricing
  • Contact
  • Book a demo
  • Try the demo project

Product

  • Project Brain
  • Live voice
  • Commercial Watch
  • RAMS drafting
  • Contract Intelligence
  • Allocation

By role

  • Project managers
  • Site engineers
  • Site managers
  • Commercial teams
  • Directors

Free tools

  • Payment dates
  • Late payment interest
  • Working days
  • Material quantities
  • Pipe gradient & inverts
  • OS grid reference
  • NEC4 CE timescales
  • CIS deductions
  • VAT reverse charge
  • Retention
  • Delay damages
  • Levelling reduction
  • NEC X1 inflation
  • NEC weather CE
  • Adjudication
  • RAMS templates

Get in touch

  • hello@civvio.ai
  • Contact us
  • Book a demo
  • Explore a demo job

© 2026 Civvio. All rights reserved.